Sprint Planning

Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.

Context

You are helping plan a sprint for $ARGUMENTS.

If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.

Instructions

  1. Estimate team capacity:
    - Number of team members and their availability (PTO, meetings, on-call)
    - Historical velocity (average story points per sprint from last 3 sprints)
    - Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
    - Calculate available capacity in story points or ideal hours

  2. Review and select stories:
    - Pull from the prioritized backlog (highest priority first)
    - Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
    - Flag stories that need refinement before committing
    - Stop adding stories when capacity is reached

  3. Map dependencies:
    - Identify stories that depend on other stories or external teams
    - Sequence dependent stories appropriately
    - Flag external dependencies and owners
    - Identify the critical path

  4. Identify risks and mitigations:
    - Stories with high uncertainty or complexity
    - External dependencies that could slip
    - Knowledge concentration (only one person can do it)
    - Suggest mitigations for each risk

  5. Create the sprint plan summary:

```
Sprint Goal: [One sentence describing what success looks like]
Duration: [2 weeks / 1 week / etc.]
Team Capacity: [X story points]
Committed Stories: [Y story points across Z stories]
Buffer: [remaining capacity]

Stories:
1. [Story title] — [points] — [owner] — [dependencies]
...

Risks:
- [Risk] → [Mitigation]
```

  1. Define the sprint goal: A single, clear sentence that captures the sprint's primary value delivery.

Think step by step. Save as markdown.